CSCS Test Question – Environmental Awareness and Waste Control

This CSCS Environment Awareness and Waste Control practice test contains 30 multiple-choice questions based on the topics covered in the CSCS Health, Safety and Environment Test. It is designed to help you improve your understanding of environmental responsibilities on construction sites and prepare for the real exam.

The questions cover key areas such as waste management, recycling, hazardous waste, pollution prevention, spill response, energy conservation, dust and noise control, wildlife protection, and environmental legislation. You will also be tested on reducing site waste, protecting watercourses, and following environmentally responsible working practices.

cscs test questions environmental awareness

Some questions have more than one correct answer. To get the mark, you must choose all the correct options. There is no time limit, so you can take your time and focus on understanding why each answer is correct. The pass mark is 27 out of 30.

1. What is a common consequence of ordering more materials than a project requires?

Question 1 of 30

2. You find a nesting bird in an area where work is due to take place. What should you do?

Question 2 of 30

3. Which two actions can help minimise energy use and reduce emissions on a construction site? (Select two answers)

Question 3 of 30

4. Under environmental legislation, who can face prosecution for failing to comply with the law?

Question 4 of 30

5. Why is protecting historic buildings and structures important?

Question 5 of 30

6. A worker may be breaking wildlife protection laws if they do which two of the following? (Select two answers)

Question 6 of 30

7. Which two of the following are classified as hazardous waste? (Select two answers)

Question 7 of 30

8. Which of these are classified as non-hazardous waste? (Select two answers)

Question 8 of 30

9. What is one of the most effective ways to control dust on a construction site?

Question 9 of 30

10. You are carrying out a noisy task and realise it cannot be completed within normal working hours. What should you do first?

Question 10 of 30

11. Which of the following represents poor environmental practice on site?

Question 11 of 30

12. Where should construction site waste normally be placed for disposal?

Question 12 of 30

13. What is the correct way to dispose of leftover concrete and concrete washout water?

Question 13 of 30

14. What does this symbol mean if you see it on a product?

Environmental Hazard

Question 14 of 30

15. Why is reducing energy consumption important? (Select three answers)

Question 15 of 30

16. What is the correct way to deal with soil that has been contaminated by leaking oil from plant or machinery?

Question 16 of 30

17. What type of pollution is most commonly associated with hand-held power tools?

Question 17 of 30

18. While excavating, you uncover several old coins. What is the most appropriate action?

Question 18 of 30

19. What is one effective way of reducing the risk of harming protected wildlife?

Question 19 of 30

20. Which activity is most likely to contribute to air pollution on a construction site?

Question 20 of 30

21. What are the two main benefits of separating waste into different categories on site? (Select two answers)

Question 21 of 30

22. Why should heavy materials not be stored beneath a tree?

Question 22 of 30

23. Which two actions are most effective at reducing waste on a construction site? (Select two answers)

Question 23 of 30

24. Which statement is correct regarding a site spill involving just one litre of oil?

Question 24 of 30

25. What should happen if an oil or diesel spill occurs on site?

Question 25 of 30

26. Which two of the following are common causes of water contamination on construction sites? (Select two answers)

Question 26 of 30

27. You need to dispose of a liquid contaminated with oil. What is the correct action?

Question 27 of 30

28. Which of the following is least likely to create a disturbance for people living or working near a construction site?

Question 28 of 30

29. Which action best helps to reduce the environmental impact of a construction site?

Question 29 of 30

30. How should hazardous waste be managed on a construction site? (Select two answers)

Question 30 of 30


 

Leave a Comment

Your email address will not be published. Required fields are marked *

Scroll to Top